Project and break bulk cargo

Cargo that does not fit a container needs a plan before it needs a price. We survey first, then quote.

Overview

Project & Break Bulk Cargo with King Freight Maritime

Project cargo is not simply large freight. It is an engineering exercise with a shipping component — the lift plan, the lashing calculation, the road survey and the port approval all have to work together before a single rupee of freight is worth discussing.

King Freight Maritime handles over-dimensional and heavy-lift movements out of Indian ports: transformers, pressure vessels, plant modules, structural steel and machinery that will not go in a box.

What is included

Route surveys

Physical surveys of the road corridor, checking bridge capacity, overhead clearance and turning radii.

Lashing and stowage plans

Securing calculations prepared and approved for the vessel and the voyage.

Lift coordination

Cranes, barges, hydraulic axles and stevedores coordinated at load and discharge.

Marine insurance

All-risk cover arranged for cargo where a single piece carries most of the value.

Port approvals

Berth applications, heavy-lift permissions and port authority coordination handled in advance.

Milestone reporting

Written progress reporting at each stage, because project cargo has stakeholders beyond logistics.

At a glance

Cargo typeTypical methodKey planning input
Over-dimensional but liftableFlat rack or open top containerExact dimensions and centre of gravity
Heavy single piecesBreak bulk on conventional vesselWeight, lifting points, lift plan
Plant modulesChartered vessel or MPPStowage plan and discharge port capability
Long structural cargoFlat rack with overhangOverhang declaration and securing plan
High-value machineryBreak bulk with marine surveySurvey report and insurance valuation

Every project movement is priced individually. Send dimensions, weight, lifting points and both addresses, and we will come back with a method statement before a rate.

Documents we will need

  • General arrangement drawing
  • Weight and dimension certificate
  • Centre of gravity and lifting point details
  • Route survey report
  • Method statement
  • Marine insurance valuation
  • Port and road permits

Frequently asked questions

When does cargo become project cargo?
When it exceeds the dimensions or weight a standard container can take, or when moving it requires equipment and permissions beyond a normal trailer and terminal. Practically, anything over about 40 tonnes per piece, or wider than roughly 3 metres, starts needing a plan rather than a booking.
How far in advance should project cargo be planned?
Six to twelve weeks is normal, and complex movements need longer. Route surveys, permits, vessel space for break bulk and crane availability all have lead times that cannot be compressed by paying more.
What is a route survey and why does it cost money?
A route survey physically checks the entire road corridor for obstructions — bridge load ratings, overhead cables, culverts, turning radii, tree lines. It costs money because it takes engineers and time, and it saves considerably more than it costs. Discovering a low bridge with a 90-tonne transformer already on the trailer is the alternative.
Do you handle the insurance?
We arrange all-risk marine cover through licensed underwriters. For project cargo we strongly recommend an independent marine warranty surveyor as well, particularly where a single piece represents most of the consignment value.
Related

Services that usually go with this

Ocean Freight

Container space on the trades Indian exporters and importers actually run, booked with named carriers and conf…

Learn more

Road Transportation

The leg that most often breaks a schedule is the one on the road. We plan it backwards from the cut-off, not f…

Learn more

Cargo Insurance

Carrier liability is not insurance. It is capped by international convention, and the cap is almost always far…

Learn more